Donations - [Project Completed] Eagle Scout Project - SunYanZi - 2012-09-26

If Paypal would kindly stop freezing my account for whatever reason, I'd gladly donate.


Donations - [Project Completed] Eagle Scout Project - Marksman Bryan - 2012-09-28

Purchased all of the necessary materials today and dropped them off at the project site - construction starts at 9:00 am EST tomorrow morning! Goal is to complete the foundation, flooring, cutting, and painting. Hopefully we can construct a few trusses as well!

I will be taking many pictures (have to document, anyway) and will be posting an update video after this weekends' work. I think it will be possible to finish the entire thing if my volunteers work hard enough!


Donations - [Project Completed] Eagle Scout Project - Marksman Bryan - 2012-09-30

Worked a total of 16.5 hours (myself) today.
Over 75 hours total from all volunteers.

What we completed today:

All trusses constructed w/ gussets
Walls constructed
Primed everything (a lot harder than it sounds holy crap)
Painted all trim (white)
Foundation and flooring leveled and completed

Tomorrow, we hope to have the walls up with the siding attached before volunteers arrive.

To do:

Paint all T1-11 siding
Mark and cut siding
Attach trusses
Attach roofing sheets
Attach shingles


[spoiler=Today's picture overview]
[Image: HQPXy.jpg]

Before volunteers got here; dug out foundation spots and filled them with limestone rocks + cement blocks for a foundation; 4x4 runners on top

[Image: bBhbX.jpg]

Picture of me working with some volunteers (little kids, had to keep them occupied for the most part lol)

[Image: pYGdK.jpg]

At the end of the day! Trusses, walls, flooring, and all of the T1-11 siding is primed and lying against the back and front of that firewood shed (which was a different kids Eagle Project along with a fire pit)
[/spoiler]


Donations - [Project Completed] Eagle Scout Project - Marksman Bryan - 2012-09-30

Started raining - end of day two
[Image: 486722_4047941835351_165252930_n.jpg]


Donations - [Project Completed] Eagle Scout Project - Marksman Bryan - 2012-10-07

Smile Done!

[Image: 547014_4077106564451_212923413_n.jpg]


Donations - [Project Completed] Eagle Scout Project - Razmos - 2012-10-07

Looks very nice, good job Big Grin


Donations - [Project Completed] Eagle Scout Project - MuscleWizard - 2012-10-07

Awesome!
Good work man.


Donations - [Project Completed] Eagle Scout Project - WillDaSnail - 2012-10-07

Very nice Bryan! Biggrin